Service Ratio
1:1.5
Staff to Guest Ratio (High Touch).
Total Units
35 Guest / 18 Staff
Balanced ecosystem capacity.
Staff Count
~28 FTE
Plus On-Call DSP Support.
The Labor Stack
Operational Roles & Flexible Housing Options
| Role / Dept | Count | Base Pay | |
|---|---|---|---|
| Leadership (GM/Chef) | 2 | $85k - $95k+ | |
| Guild Masters (Artisans) | 4 | $60k+ | |
| DSPs (Direct Support) | 4-6 | $30/hr+ | |
| Ops & Hospitality | 12 | $25/hr | |
| Grounds & Agriculture | 6 | $25/hr | |
| TOTAL FTE | ~28 | Includes DSP Coverage | |
Housing Philosophy
The Honeycomb Cluster
We arrange our Guild Halls in a hexagonal "Honeycomb" formation. This biomimetic layout maximizes shared community space in the center while directing private views outward to nature. It creates a grounded, balanced environment that works with the landscape, not against it.
The DSP Role
Direct Support Professionals act as "Personal Concierges" or friends-in-residence. They operate under strict NDA and HIPAA compliance. Their housing can be integrated near guests for on-call support or separate for downtime.
3x Guild Halls (The Honeycomb)
24 Beds • Hexagonal Cluster
Three distinct halls (8 suites each) arranged in a hexagonal pattern. Maximizes connection
and privacy.
Phase 2 Expansion: 3 additional
hexagonal halls for local affordable housing stock.
Family Cottages
2-3 Bed Units
Private residences for staff with children, partners, or specific space needs. Allocated based on family size and availability.
Ag-Outpost
Seasonal • 6 Beds
Short-term housing for seasonal farm apprentices and summer support crew.
Phased Rollout
Phase 1: Foundation (Months 1-6)
Secure temporary housing (RVs/Airstreams) for construction crew. Begin construction of Guild Hall A (The First Hexagon).
- • Hire: Project Manager, Lead Carpenter
- • Build: Utility hookups for staff zone
Phase 2: Activation (Months 6-12)
Completion of the Staff Honeycomb (3 Halls). Hiring of core operational team (GM, Chef, DSPs). They move in 2 months pre-opening.
- • Hire: GM, Chef, 4 Artisans, 2 DSPs
- • Build: First 3 Family Cottages
Phase 3: Stabilization & Community (Year 2)
Expansion of housing stock. Constructing the second Honeycomb Cluster (3 Halls) dedicated to local affordable housing.